In November 2019, EDS-Development signed a Memorandum of cooperation and partnership with the Mezhivska village council (Dnipropetrovsk oblast). The purpose was the implementation of business projects (construction of industrial solar power stations) on the territory of Mezhivska OTH (amalgamated territorial community), tax deductions from which will be used to improve the socio-economic situation in the region.
One of the projects under the agreement is a land pot with an area of 185 ha, which our company is preparing for the construction of a large industrial solar power station with a capacity of 100 MW.
Large-scale projects are being successfully implemented in Ukraine. In 2019, for example, 200 MW Nikopolskaya SPS and 240 MW Pokrovskaya SPS (the second largest in Europe) were commissioned.
Let's take a closer look at these projects:
| Large SPSs in Ukraine | Nikopolskaya SPS 200 MW | Pokrovskaya SPS 240 MW |
|---|---|---|
| Investment amount | 216 000 000 euros (135 million euros of which were invested by CMEC + 81 million euros from DTEK) | 193 000 000 euros |
| Investor | Ukrainian Solar Farm-1 (DTEK), Chinese China Machinery Engineering Corporation (CMEC) | Solar Farm LLC - 3 (DTEK) |
| Contractor | Chinese China Machinery Engineering Corporation (CMEC). Construction period: April 2018 - March 2019 - 11 months. | 16 Ukrainian enterprises received orders for EUR 48,000,000. Construction period: April 2019 - October 2019 - 7 months. |
| Generation/tariff/income | 290,000,000 kWh per year, tariff 15.03 euros per MWh, income - 43,587,000 euros per year. Payback - 5 years. | 400,000,000 kWh per year, tariff 15.03 euros per MWh, income - 60,120,000 euros per year. Payback - 3 years. |
In addition to the conclusion that large projects are being successfully implemented in Ukraine, we can make some simple calculations for our 100 MW project right now:
Investment amount
82,000,000 euros is the amount of investment required for a 100 MW project.
Investors
Most likely, it is necessary to attract foreign investors, the amount of necessary investments is large.
Contractors
You can safely involve Ukrainian companies as an EPC contractor (general contractor), or for partial tasks. As we saw on the example of Pokrovskaya SPS, Ukrainian companies out-did their Chinese colleagues:
240 MW in 7 months and 193,000,000 euros (Ukrainian contractors)
versus
200 MW in 11 months and 216,000,000 euros (Chinese contractors)
Nice to see such results!
Generation/tariff/income
Generation on average is 145 000 000 kWh per year for our 100 MW facility;
The project will participate in the Auction, the projected tariff rates are from 8 to 10 euros per MWh;
Annual income for 100 MW SPS will amount to 11 600 000 euros per year (with an 8 euros’ tariff);
Payback is 7 years.
Description of the Ready to build land plot, ready for construction of a SPS by EDS-Development
Location - Ukraine, Dnipropetrovsk oblast, Mezhivskyi district, Mezhova urban-type village.
Status - Rent for 49 years. Realization through the sale of corporate rights.
Area – 185 ha
The cost of the plot - 2 500 000 euros without TU (technical conditions).
The cost of TU (technical conditions) - 6 000 000 euros.
Designated purpose - 14.01
Cadastral number - 1222687700:01:002:0466; 1222687700:02:002:0715; 1222687700:02:002:0711
TU (technical conditions) - 100 MW
Documents:
- Feasibility study.
- Draft technical conditions.
- Detailed territory plan.
- PV layout.
- Developed topographic and geodetic survey.
- Land management project.
Infrastructure - Connection point: overhead line, 110 kV voltage class.