EDS-DEVELOPMENT has begun the final stage of the construction of the Makov-1 solar power station in the Dunaevets district of the Khmelnytskyi region. The vast majority of the planned work has already been completed, it remains to improve the territory of the facility.
Recall that the total capacity of the newly built MES-1 SPS with an area of 20 hectares will be 9.99 MW, which will provide clean solar energy to industrial and residential consumers in the surrounding settlements.
Thanks to proper planning, all construction, and electrical installation work are carried out in parallel, which allows you to adhere to the scheduled deadlines for the commissioning of the object.
Note that all 41768 pieces. FEM (PV modules) and 151 pcs. the inverters provided by the design and technical documentation of the SPS are installed. The installation of 6 transformer substations KTP 0.4\10 kV and distribution point RP-10 kV was also completed.
Landscaping is being actively carried out: roads are being built inside the site and the installation of the entrance fencing group around the perimeter of the solar power station is in the final stage.