EDS-DEVELOPMENT continues to actively build the second phase of a 2 MW solar power station Lybid with a total capacity of 5,1 MW.
Also, the work began on the development of a panel field for the third phase of the SPS.
The first phase of the 2.1 MW Lybid SPS, erected by EDS-DEVELOPMENT, was launched in March this year and have already compensated the customer for the investments made. The new line of the solar power station will be connected to the networks with the help of a substation recently reconstructed by the specialists of the EDS-DEVELOPMENT.
The calculation of the completion date for the construction of the second stage is SPS September of 2019.