The EDS group completed the construction of the 0.975 MW solar power plant in Hrebinka city, Poltava oblast.
By this technical solution of a compact solar power plant, the EDS team confidently declares that it is ready for changes in the Ukrainian sun market in 2020*
- * SPP built from January 1, 2020 with a capacity of up to 1 MW are not required to participate in auctions and can issue a “green” tariff, receiving 0.113 Euro per kWh guaranteed by the state.
Project details:
- 3094 JA Solar photovoltaic modules 380 W each;
- 13 SMA string inverters with a capacity of 75 kW each;
- to transfer alternating current in the Poltavaoblenergo grid, a packaged transformer substation PTS-1000/10/0.4 kV was built;
- connection to the distribution company grids is made using a 0.4 kV cable line;
- the facility is equipped with monitoring systems, video surveillance, burglar alarms and lighting.
Ground-based solar power plant Hrebinka is a great example of the professional work of the EDS team!