Company DEVELOPMENT completed the first phase of the construction of the Sun Energy Mezhirich solar power station (capacity 2 MW).
The construction is carried out in stages, after the completion of two more phases of the project, the total capacity of the SPS will be 7 MW. Today, the station produces about 2.5 million kWh per year. This is enough to provide green energy for a small city.
EDS-DEVELOPMENT has completed a full construction cycle from the design stage to the commissioning of the solar power plant. The design department carried out engineering geodetic and geological surveys, based on which he developed design estimates for the power station and a package of permits, without which it is impossible to begin construction.
The company’s wiring teams installed supporting structures on the territory of the power plant, which housed over seven thousand photovoltaic modules. To obtain AC voltage, Huawei inverters were mounted. They have a high energy efficiency category A + and long service life of up to 20 years.
A large percentage of the equipment installed at the facility was developed by EDS-DEVELOPMENT. The company’s specialists installed the EDS totalizers and the KTP-35 / 0.4kV complex transformer substation of their production. Similar products were used in dozens of completed projects, where they demonstrated high quality and reliability during operation.
To connect the facility to external power networks, a recloser unit with a vacuum circuit breaker and built-in current transformers is installed, which automatically disconnects a section of the circuit in case of overloads.
In the near future, the start of the second phase of construction is planned, which will increase the generated capacity by half - up to four megawatts.