The EDS group begins the year with signing a contract for the construction of a new 8 MW solar power plant in Kharkiv oblast on the territory of Birky village council, Zmiivs'kyi district near Birky village. In this project we are the general contractor - this is full control over the progress of construction and obligation to build a solar power plant.
As a reminder, in 2019 we have completed the construction of two SPP in this district with a total capacity of 6.2 MW – “Solar Solution”. The projects used the EPCM cooperation format (general contract with a financial guarantee to achieve contracted technical indicators for electricity generation).
Parameters of the future SPP Borki-3:
- 28120 TALESUN PV modules with a unit capacity of 340 W;
- 296 string inverters Fronius ECO with a unit capacity of 27 kW;
- 29 0.4 kV adders of various capacity manufactured by EDS;
- 4 packaged transformer substations KTP 10 / 0.4 kV along with 1 distributing point RP 10 kV.