The construction work related to the installation of metal structures (tables), which are subsequently mounted on photovoltaic modules (FEM), is being completed at the Makov-1 SES facility (Makovskaya village council, Dunaevets district, Khmelnytsky region). 99 percent completed:

  • Drilling holes under racks;
  • Concreting and installation of racks of tables;
  • Installation and concreting of elevated formwork.

Soon, the delivery of FEM from Jinko Solar (China), model JKM270PP-60 with a power of 270 watts, is expected.

EDS-DEVELOPMENT construction crews are simultaneously preparing the foundation for the KTP 0.4/10 kV. The concreting process is 50% complete.

Wiring teams completed the installation of cable products with a voltage class of 10 kV. At the moment, cable-conductor products are being installed with a voltage class of 0.4 kV and an inverter ground loop (75% completed).