EDS-DEVELOPMENT is completing the first phase of construction of the Lybid solar power station with a capacity of 5.1 MW in the village of Dubovoye, Sinelnikovsky district, Dnipropetrovsk region. We want to remind that the work on the SPS project began in October.
All construction and electrical work are carried out in three phases. The inverters and totalizers have already been fully installed. The installation and connection of 17 km of PV 1×6 mm2 solar cables have been completed, all 180 tables for photovoltaic modules have been installed.
Work on the installation of the FEM continues - out of 6840 modules, 5770 were mounted (over 84%). There is a switching of panels into thongs on tables – 96 out of 180 tables have already been connected (more than 53%). The company’s specialists also started connecting the cable network to inverters and summers, the cable channels of transformer KTP No. 1 are being actively installed.
We expect that by the spring of 2019, residents of the Dnipropetrovsk region will be provided with environmentally friendly solar energy.