З чого складається ціна на землю Ready to build під будівництво СЕС?

Implementation algorithm of a land preparation for the SPS construction or what does the Ready to build land price consist of

Why the land plots for the SPS construction is a standalone product?

Because land preparation is a long and expensive process. There are problems of going through a series of confusing bureaucratic procedures, which, as a rule, significantly increase the risks.

 

Regardless of what type of station you are planning to build, preparing a complete package of documents for a land plot is a rather long and problematic procedure. Not every entrepreneur is morally ready to go through it, which, in principle, can influence the decision to build a facility.

документи на землю під сес

Let's consider in more detail the steps that must be passed to prepare a land plot for the construction of an industrial solar power station:

  • Development of the project concept.
  • Set up a legal entity.
  • Choosing a land plot for construction.
  • Development and coordination of a detailed plan of the territory.
  • Development and coordination of a FS for connecting the facility to power grids.
  • Determination of the technical feasibility of connecting the facility to external power grids.
  • Execution of topographic-geodetic and engineering-geological surveys.
  • Conclusion of a land lease agreement or acquisition of ownership.
  • Development and coordination of the land allocation project with the "energetic sector lands" designated purpose.
  • Conducting public discussions (hearings) on the construction of the facility.
  • Obtaining technical specifications for connecting the facility to external power grids.
  • Obtaining urban planning conditions and restrictions.
  • Obtaining permits for design and technical specifications (ecology, fire safety, etc.).
  • Payment for connecting the facility to the electrical grids.
  • Development and coordination of a project for connecting the facility to electrical grids.
  • Obtaining a positive findings of a project in expert institutions.
  • Development and coordination of the facility construction project.
  • Obtaining a permit to start construction and installation work for the construction of external electrical grids.
  • Preparation for auctions for over 1 MW projects.
  • Formalization of a "green" tariff for ≤ 1 MW projects.

To optimize the process, everything that the procedure allows is performed in parallel - in more detail the implementation algorithm in the order of processes can be seen in the diagram:

документы для земли под сэс
Stage:Timing:
1Development of the project conceptindividually, depends on the maturity of the project
2Set up a legal entity1-2 weeks
3Choosing a land plot for construction2-3 weeks
4Development and coordination of a detailed plan of the territory.2 month**
5Development and coordination of a FS for connecting the facility to power grids.3-6 months*
6Determination of the technical feasibility of connecting the facility to external power grids.2-4 weeks
7Execution of topographic-geodetic and engineering-geological surveys.14 - 21 days
8Conclusion of a land lease agreement or acquisition of ownership.* included in the FS stage
9Development and coordination of the land allocation project with the "energetic sector lands" designated purpose.4-6 months
10Conducting public discussions (hearings) on the construction of the facility.* included in the FS stage
11Obtaining technical specifications for connecting the facility to external power grids.1 month
12Obtaining urban planning conditions and restrictions.** in parallel with the Detailed plan
13Obtaining permits for design and technical specifications (ecology, fire safety, etc.).from 1 month, * included in the FS stage
14Payment for connecting the facility to the electrical gridsin parallel with the TR
15Development and coordination of a project for connecting the facility to electrical grids.1,5-2 months
16Obtaining a positive findings of a project in expert institutions.1,5-2 months
17Development and coordination of the facility construction project.2-3 months
18Obtaining a permit to start construction and installation work for the construction of external electrical grids.1-2 months

Ready to Build land for industrial solar power stations from 1 to 100 MW is presented in the EDS-Development database.

The plots have a Full package of documents, for the preparation of which our company is fully responsible!

More than 35 facilities in different regions of Ukraine.

документи на землю під сес

In addition to our own Ready to build land base , our specialists will provide services for the full or partial preparation of your land plots for the SPS construction: registration of a full permission documentation package.