EDS-DEVELOPMENT participates in a project for the construction of a solar power station with a total planned capacity of 19.9 MW in Zaporizhia.
EDS-DEVELOPMENT provides power supply to the facility, namely, it builds 11 complete transformer substations of KTP 35/0.48 kV, a distribution center of 35 kV, and also builds 1100 meters of a 35 kV cable line.
To date, the following works have been completed on the territory of the future SPS:
- all pits dug for the organization of mass receivers 11 KTP;
- made concrete preparation for all pits;
- the bottoms of five mass receivers are concreted and reinforced, and four of them already have reinforced walls;
- EDS-SOLAR is now installing wall formwork for mass receivers.
Under the 1100-meter cable line of 35 kV, the construction and installation teams of the company are preparing the sand trench. Already passed 172 meters of trench (15.6%). Excavation work is scheduled to be completed before mid-February.
In parallel, EDS-DEVELOPMENT is working on landscaping the property. We will inform you about all new construction details.
