Why the land plots for the SPS construction is a standalone product?
Because land preparation is a long and expensive process. There are problems of going through a series of confusing bureaucratic procedures, which, as a rule, significantly increase the risks.
Regardless of what type of station you are planning to build, preparing a complete package of documents for a land plot is a rather long and problematic procedure. Not every entrepreneur is morally ready to go through it, which, in principle, can influence the decision to build a facility.

Let's consider in more detail the steps that must be passed to prepare a land plot for the construction of an industrial solar power station:
- Development of the project concept.
- Set up a legal entity.
- Choosing a land plot for construction.
- Development and coordination of a detailed plan of the territory.
- Development and coordination of a FS for connecting the facility to power grids.
- Determination of the technical feasibility of connecting the facility to external power grids.
- Execution of topographic-geodetic and engineering-geological surveys.
- Conclusion of a land lease agreement or acquisition of ownership.
- Development and coordination of the land allocation project with the "energetic sector lands" designated purpose.
- Conducting public discussions (hearings) on the construction of the facility.
- Obtaining technical specifications for connecting the facility to external power grids.
- Obtaining urban planning conditions and restrictions.
- Obtaining permits for design and technical specifications (ecology, fire safety, etc.).
- Payment for connecting the facility to the electrical grids.
- Development and coordination of a project for connecting the facility to electrical grids.
- Obtaining a positive findings of a project in expert institutions.
- Development and coordination of the facility construction project.
- Obtaining a permit to start construction and installation work for the construction of external electrical grids.
- Preparation for auctions for over 1 MW projects.
- Formalization of a "green" tariff for ≤ 1 MW projects.
To optimize the process, everything that the procedure allows is performed in parallel - in more detail the implementation algorithm in the order of processes can be seen in the diagram:

№ | Stage: | Timing: |
---|---|---|
1 | Development of the project concept | individually, depends on the maturity of the project |
2 | Set up a legal entity | 1-2 weeks |
3 | Choosing a land plot for construction | 2-3 weeks |
4 | Development and coordination of a detailed plan of the territory. | 2 month** |
5 | Development and coordination of a FS for connecting the facility to power grids. | 3-6 months* |
6 | Determination of the technical feasibility of connecting the facility to external power grids. | 2-4 weeks |
7 | Execution of topographic-geodetic and engineering-geological surveys. | 14 - 21 days |
8 | Conclusion of a land lease agreement or acquisition of ownership. | * included in the FS stage |
9 | Development and coordination of the land allocation project with the "energetic sector lands" designated purpose. | 4-6 months |
10 | Conducting public discussions (hearings) on the construction of the facility. | * included in the FS stage |
11 | Obtaining technical specifications for connecting the facility to external power grids. | 1 month |
12 | Obtaining urban planning conditions and restrictions. | ** in parallel with the Detailed plan |
13 | Obtaining permits for design and technical specifications (ecology, fire safety, etc.). | from 1 month, * included in the FS stage |
14 | Payment for connecting the facility to the electrical grids | in parallel with the TR |
15 | Development and coordination of a project for connecting the facility to electrical grids. | 1,5-2 months |
16 | Obtaining a positive findings of a project in expert institutions. | 1,5-2 months |
17 | Development and coordination of the facility construction project. | 2-3 months |
18 | Obtaining a permit to start construction and installation work for the construction of external electrical grids. | 1-2 months |
Ready to Build land for industrial solar power stations from 1 to 100 MW is presented in the EDS-Development database.
The plots have a Full package of documents, for the preparation of which our company is fully responsible!
More than 35 facilities in different regions of Ukraine.