EDS-DEVELOPMENT has started the final phase of the construction of the first stage of the 1 MW solar power station in Grebenka in the Poltava region. 82% of the total project implementation work is completed. Завершено 82% общего объема работ по реализации проекта. Завершено 82% общего объема работ по реализации проекта.
Work is underway on a site of 2 hectares. Recall that our company performs turnkey construction as a general contractor. According to plans, the project will be completed before the end of the autumn of this year. To transfer alternating current, a complete transformer substation KTP-1000/10/0.4 kV will be built in the Poltavaoblenergo network, and the connection to the distribution company's networks will be made using a 0.4 kV cable line. To date, the development of the photofield is completed. Installation of power lines and a cable-conductor group is coming to the end, as well as commissioning of systems, monitoring, video surveillance, burglar alarms, and lighting.