Construction of SPS Razumovka

промышленные солнечные электростанции
промышленные солнечные электростанции

EDS-Development is building a 4 MW solar power station in the Zaporizhzhya region on the territory of the Razumovsky village council. 20% of all planned work has already been completed.

Now on the site is in working position the parallel installation of metal structures of tables and their installation. We are using our own special equipment.

The new alternative energy facility will be completed by the end of October this year.

The construction of a 1 MW SPS Grebinka is nearing completion

промышленные солнечные электростанции
промышленные солнечные электростанции

EDS-DEVELOPMENT has started the final phase of the construction of the first stage of the 1 MW solar power station in Grebenka in the Poltava region. 82% of the total project implementation work is completed. Завершено 82% общего объема работ по реализации проекта. Завершено 82% общего объема работ по реализации проекта. 

Work is underway on a site of 2 hectares. Recall that our company performs turnkey construction as a general contractor. According to plans, the project will be completed before the end of the autumn of this year. To transfer alternating current, a complete transformer substation KTP-1000/10/0.4 kV will be built in the Poltavaoblenergo network, and the connection to the distribution company's networks will be made using a 0.4 kV cable line. To date, the development of the photofield is completed. Installation of power lines and a cable-conductor group is coming to the end, as well as commissioning of systems, monitoring, video surveillance, burglar alarms, and lighting.

730 days of reliable operation

строительство сэс, инвестиции в сэс, солнечная электростанция, ФЭМ
промышленные солнечные электростанции

Today is exactly two years from the date of commissioning of SPS «San Energy» 2 MW when the first solar power station was built by EDS-DEVELOPMENT.

At the very beginning of July 2017, the EDS team took the first step on the long road of building the industrial solar power station. A step in 2 megawatts was built, which after less than two years increased to 75 MW. Our company has built it only in the first quarter of 2019. Today, the total capacity of the orders that we attract is measured in tens of megawatts per month. But that is now. And it all got started with SPS “San Energy”.